Charger Commissioning: Final Documentation Step

Complete your Noah Energy charger commissioning record by accessing the online form, verifying your charger information, uploading required evidence, and submitting it for review.

Before You Begin

Commissioning should be completed by a trained, qualified installer or services professional. Before starting, have the following ready:

  • Charger model number and serial number

  • Installer company and technician details

  • Required photos, screenshots, and commissioning evidence

  • Site name, address, and planned charger location / stall ID

  • CPO / CPMS provider, OCPP settings, and Charge Point ID

  • Internet access by cell phone, Wi-Fi, hotspot, or approved connection

Types of Evidence to Upload

Site

  • Overview photo
  • Installed charger location
  • Planned stall / charger ID

Product

  • Nameplate / serial number
  • Powered on charger photo
  • Firmware screen

Electrical

  • Breaker / panel
  • Conduit entry
  • Grounding / bonding
  • Power terminations

Network / CPMS

  • Ethernet or SIM evidence
  • Signal screenshot if cellular
  • CPMS online confirmation
  • OCPP / Charge Point ID
    This website is used to submit commissioning records, product information, site information, and required evidence. It does not replace the released AC or DC commissioning procedure, installation manual, or required electrical safety verification steps.